Environment

Waste infrastructure update

NImapThree projects under the waste infrastructure programme are working to significantly different timelines. Stephen Dineen outlines recent developments.

All three waste management groups are still involved in a competitive dialogue process for waste infrastructure projects but contrasting timelines exist for the three plans.

The Southern Waste Management Partnership (SWaMP2008) expects to award its contact for mechanical biological treatment (MBT) by April 2013 but has no construction timeline at present.  The North West Region Waste Management Group (NWRWMG) hopes that its MBT and energy recovery facilities will become operational by the end of 2014. arc21 does not expects its MBT and energy from waste project to start operating until 2017-2018.

The Northern Ireland Waste Management Strategy 2006-2020 envisages waste management facilities at a limited number of key sites. Energy recovery is identified as an alternative treatment method to landfill.

By 2020, a limit of 35 per cent of 1995 levels of biodegradable municipal waste will be allowed go to landfill. Under the 2008 revised Waste Framework Directive, by 2020, 50 per cent of household waste will have to be prepared for re-use and recycling.

A DoE spokeswoman told agendaNi that while there has been “a degree of slippage in project delivery, overall changes in wastes arising, increases in recycling and other factors have also reduced the immediate pressure to have facilities operational as early as previously forecast.” The department is confident that 2020 landfill diversion obligations will be met.

Procurement processes are not owned by the department so it cannot set deadlines for awarding contracts. It has funded all costs so far (e.g. specialist financial, technical and planning advice), which totalled £9 million in procurement costs up to 31 March 2012. Funding is tied to procurement milestones but these are subject to revision.

The spokeswoman pointed out that this expenditure needs to be considered against total costs and “the potential financial consequences of any error at the negotiation stage.”

She added that benchmarking comparisons from two sources (data from projects in Great Britain and Defra’s Waste Infrastructure Programme) show that procurement costs here compare favourably with similar scale projects elsewhere in the UK. The department declined to release the information, citing commercial confidentiality.

Meanwhile, in February, the department warned against Energy Minister Arlene Foster’s proposals to redefine advanced gasification technologies (as proposed for NWRWMG) and amend the renewables obligation certificates (ROCs) levels for such energy sources.

In a submission to DETI, it stated that the tender bid for NWRWMG’s infrastructure project was predicated on the ability of the technology to achieve two ROCs from advanced gasification.

“There is a strong possibility that redefining the plant to standard gasification and reducing the level of its ROC support to 0.5 could render it no longer economically viable,” the letter stated.

In August, the proposal to reduce ROCs for the standard band of advanced conversion technology from one to 0.5 was dropped. The standard and advanced bands will be merged from 1 April 2013 and new accreditations and additional capacity will receive two ROCs until 2015-2016.

 

ARC21


ARC21

Formally established in 2003, arc21 was the first waste management group of its kind
in the UK.
arc21’s waste management plan proposes to use MBT and energy from waste (EfW) in its development of new waste infrastructure.
Under the plan, residual waste will be sent to an MBT facility, where recyclable and
re-useable material is recovered mechanically, with remaining material then used as fuel at the EfW facility to produce heat or electricity. The total project value is estimated at
£1 billion.
The procurement process commenced in September 2008 and is continuing. Facilities are expected to become operational during 2017-2018. Once a contract is awarded, management of residual waste will be managed by the successful bidder using interim arrangements while permanent facilities are being developed.

NWRWMG

NWRWNG

Formed in 1999, NWRWMG is co-ordinating a £500 million procurement project, the process for which commenced in 2009.
It aims to develop energy recovery facilities with capacity to deal with approximately 70,000 tonnes of waste per year and MBT facilities with a capacity of 140,000 tonnes of waste per year. A consortium comprising Brickkiln, United Utilities and Sisk is at the final stage of the procurement process.
NWRWMG has ruled out using incineration but either gasification, pyrolysis or cement kiln processes will be used. The group expects to announce more details, including locations, later this year, with the new facilities due to become operational before the end of 2014.

SWaMP 2008

SWAMP

Originally called SWaMP, the partnership was formed in 2000.  In June 2009, SWaMP2008 commenced its procurement process. Following the withdrawal of three operators, the group has been in discussions with one bidder, Quinn Group Holdco Limited, since April 2011.
Quinn Group Holdco Limited has proposed two new partners for the group: UK construction and engineering firm Costain Group and investment and development company Equitix. Quinn Manufacturing Group is expected to replace the Quinn Group Holdco Limited.
The bidders have proposed a network of five waste transfer stations, combined with an MBT facility at a site in Lisbane, in County Armagh, which has planning permission. Quinn Manufacturing will take away the solid recovered fuel from the MBT plant to be used at a Quinn cement kiln in the Republic.
The partners envisage that operational delivery will be split between Quinn Manufacturing Group Limited and Costain, with Costain primarily responsible for operating the MBT plant and overall provision of services.
The contract is worth approximately £500 million.